Laying HDPE Pipe Line From Nabisar to Thar Coal Km 10+000 To Km 20+000
| Total Contract Value: | Pak Rs. 1,948 Million, US$ 18.73 Million. |
| Contract Periods: | August 2014 to August 2015. |
| Employer: | Office of the Executive Engineer, Water Carrier Work Division, Mirpurkhas. |
| Consultant: | A.A. Associates. |
| Brief of Project: | Laying HDPE pipe line from Nabisar to Thar Coal Km 10+000 to Km 20+000, Purpose of the HDPE Pipe Line Supply of Treated Water for Thar Coal Project Area. |